Realization of the Demonstration Project allows achieving of the following results:
- Energy Efficiency and Economical effect
- Heat loading will increase 3 times (from 23 Gcal/h - 60 Gcal/h);
- 2,5-3,0 MW/h of electricity additionally will be supplied to the city electricity network;
- 80% of electricity for own needs of the DHC "KomunEnergia" will be produced by itself during winter-time;
- 2,0 MW/h of electricity for own needs of the DHC "KomunEnergia" will be covered by own production during summer-time;
- The reserved amount of 2,9 MW/h is planned to realize in trolley-buss department and CE "Misksvitlo".
- Ecological (Environmental) Effect;
- Shut down (closure) of 6 outdated, no effective Heat Individual Boiler Stations.
- Social effect.
- Increased quality services to Rivne inhabitants. Permanent (12 month a year, 7 days a week, 24 hours a day) and steady:
- Hot water supply to the central part of the town of Rivne;
- Hot water supply to the district "Pivnichniy"in the town of Rivne;
- Heat supply to the central part of the town of Rivne;
- Hot water supply to the district "Fabrichniy: in the town of Rivne.